|
General contractor Chris R. Sheridan & Co., Macon, GA
and pumping contractor Cherokee Pumping Company, Stockbridge,
GA, completed a challenging concrete project at the Boeing
Aerospace facility in Macon in November 2002.
The facility is scheduled to house two new Brotje Integrated
Panel Assemby Cell (IPAC) Riveters. The riveters, the largest
models in the world, will be used in the fabrication of fuselage
panels for the C-17 Globemaster III, Boeings military
transport aircraft. Sheridan was contracted to design and
construct the foundations needed to support these massive
machines.
Sheridan, a general contracting, construction management and
design-build business since 1947, has a 12-year client-contractor
relationship with industry giant Boeing. From the beginning,
Tom Rogers, a representative for Sheridan, understood this
particular project would be a challenge.
The coordination of a 505-cubic yard indoor monolithic slab
pour, one of the largest in the contractors history,
was a real test. "From the beginning, it was a coordination
nightmare," said Rogers. "The manufacturer couldnt
afford to shut down production while we completed this job
for them. We had a schedule to keep, and we had to figure
out how to finish our work without disrupting theirs."
Sheridan contracted Cherokee Pumping Company and used its
own placing and finishing crew to complete the 505-cubic yard
monolithic mat pour inside the building. "We scheduled
the pour on a Saturday when production at that particular
facility was minimal," said Rogers, "That allowed
us to drive right up inside the enclosed building and position
the pump right next to the pour."
A restricted ceiling and entry height posed a challenge for
Cherokees truck-mounted concrete pump and ready mix
trucks from LaFarge Ready Mix, Macon, GA. Space for the concrete
pump was tight. The X-Style outriggers set up in an economical
19.75 by 24.5-feet. With a low unfolding height of 25 feet,
4 inches, the 4-section roll-and-fold boom cleared ceiling
beams and pumped the project in 5 hours.
Cherokee Pumping owner Wayne Bylsma says he compared the advantages
of utilizing the Schwing roll-and-fold boom versus the Z-boom.
"The ceiling height was obviously a factor, but Z-booms
arent the only way to go. After all, roll and fold and
Z-booms have the same unfolding height. When beams and electrical
components in the ceiling need to be avoided, the 32-meter
Schwing did the job with no hassles. Plus with the Roll and
Fold design we didnt have to reconfigure the boom to
prime it. That would have been a problem for a Z-boom in these
tight conditions."
Equipped with the patented Schwing Rock Valve and a
Generation III pump kit, the 32 maintained smooth, strong
concrete output throughout the pour. Low noise levels of these
features were also valuable in the facility while Boeing employees
continued to work.
According to Chuck E. Smith, Senior Sales Manager with LaFarge
Ready Mix in Macon, GA, ready-mix design was also a special
consideration. At around 4,000 psi, super-plastisizer was
added to create a workable mix for finishers. "We had
about a 45-minute window, and then it slumped tight,"
said Smith.
Trucks made round trips to and from two of LaFarges
nine area ready mix plants for reloading. "It was really
convenient," said Smith, "The Boeing plant just
happened to be smack dab in the middle of the two sites. We
had 15 trucks making relatively short trips."
The final concrete foundations are two mass slabs. Each slab
is supported by 44 cassions in a pit measuring 43 feet wide,
80 feet long, and 15 feet deep. More than 35,000 pounds of
reinforcing steel and 505 cubic yards of concrete, are incorporated
into the two foundations.
With the Boeing project behind him, Bylsma has a true appreciation
for Schwing booms. Cherokee bid for another project in December
2002, a 5-month series of indoor pours at the Honda manufacturing
plant in Lincoln, Alabama. Project owners required big output
numbers over an extended period. With a 25-foot ceiling height,
bidding contractors had to come prepared with the most versatile
equipment that could adapt to the job.
Job specs prompted Bylsma and company to purchase a brand
new Schwing S 31 HT the same month. The small 205"
by 245" footprint and maneuverability provided
an important advantage on the tight job site and convenient
relocation. Offering the project owners the versatile 5-section
telescopic boom with an unfolding height of 188"
was instrumental in Cherokee being awarded the job.
The project began February 5th, and Bylsma estimates that
the 31-meter will pump 7,000 yards per month over a 5-month
period. "It was the only way to go for this particular
job," said Bylsma, "This is the only model that
could complete those numbers and work under these conditions.
It was a great investment."
The investment was such a good one that Bylsma has plans to
purchase his second S 31 HT in the next few months. "Everyone
knows we have this unique boom and they want it. Its
not just an indoor pump. The 31-meter allows me to set up
outside of buildings and telescope right in to finish a pour
precisely where its needed without adding slickline.
Its also a great piece of equipment for house foundations.
For a pumping contractor, versatility is priceless."
|